The existing diamond was cut into three pieces and as an excavator pried the sections loose, each panel was moved out of the immediate work area. 4/12/2016 - 598C6368dK
139 / 372

The existing diamond was cut into three pieces and as an excavator pried the sections loose, each panel was moved out of the immediate work area. 4/12/2016 - 598C6368dK

  • The existing diamond was cut into three pieces and as an excavator pried the sections loose, each panel was moved out of the immediate work area. 4/12/2016 - 598C6339dK
  • The existing diamond was cut into three pieces and as an excavator pried the sections loose, each panel was moved out of the immediate work area. 4/12/2016 - 598C6344dK
  • The existing diamond was cut into three pieces and as an excavator pried the sections loose, each panel was moved out of the immediate work area. 4/12/2016 - 598C6368dK
  • Final trimming on the new diamond. 4/12/2016 - 598C6385dK
  • Once the old diamond was removed, ballast was laid and smoothed to depth. 4/12/2016 - 598C6379dK
  • Once the old diamond was removed, ballast was laid and smoothed to depth. 4/12/2016 - 598C6415dK
  • The new diamond panel was picked up and slid into place by the crane and the excavator. 4/12/2016 - 598C6436dK
  • The new diamond panel was picked up and slid into place by the crane and the excavator. 4/12/2016 - 598C6475dK